Update for road closures on Stoltz Hill and Vaughan

This notice serves as an update to the Notice of Street Paving issued June 8 regarding
work to be performed on Stoltz Hill Road.
Stoltz Hill Road between Walker Road and Vaughan Lane was originally scheduled to be
closed on Tuesday, June 21, and Wednesday, June 22, for final paving. Due to equipment
difficulties, this paving operation was temporarily delayed. The closure is now scheduled to
begin Wednesday, June 22, and last through Friday, June 24. Construction closures on
Vaughan Lane will not go into effect until paving on Stoltz Hill Road has concluded.

This notice serves as an update to the Notice of Construction and Road Closure issued June
15 regarding work to be performed on Vaughan Lane.
The closure on Vaughan Lane between Stoltz Hill Road and 7th Place was originally
slated to begin Wednesday, June 23. Due to delays with construction on Stoltz Hill
Road, this closure will not begin until Monday, June 27. As stated in the press release
from June 15, this closure is anticipated to last until mid-October.
As indicated in the previous press release, the section of Vaughan Lane from South Main
Road to Quail Place is closed to through traffic (with a detour route) for a private development. This closure is still anticipated to last until July 15.

For continuous updates regarding construction locations, please see the City of Lebanon
website at https://www.ci.lebanon.or.us/gis.
We appreciate your patience and cooperation as we perform the necessary work. If you have any questions or concerns, please contact Engineering at 541-258-4923 or
[email protected]